Team 1
Scrum Master this week: Jalen
Committed Effort
37 pts
24 claimed stories
Completed Velocity
37 pts
24 done (100%)
In Flight
0 pts
0 in Design / Impl / Test
Waiting on Deps
0
0 queued in sprint backlog
Velocity & Iteration Burndown
Team 1 Velocity
Committed vs. completed points per sprint
| Sprint | Committed | Done | In-Flight | % |
|---|---|---|---|---|
| I1 | 5 | 5 | 0 | 100% |
| I2 | 2 | 2 | 0 | 100% |
| I3 | 11 | 11 | 0 | 100% |
| I4 | 19 | 19 | 0 | 100% |
Team 1 Burndown
I4 · 2026-10-28 to 2026-11-11
What this team is building (24)
I1Wed, Sep 16, 2026 to Wed, Sep 30, 20260 open · 5/5 pts done · 0 must
Public Site
Done1 ptsPublic Site
Done1 ptsPublic Site
Done1 ptsAccounts
Done1 ptsAccounts
Done1 pts
I2Wed, Sep 30, 2026 to Wed, Oct 14, 20260 open · 2/2 pts done · 0 must
Property Inputs
Done1 ptsCalculations
Done1 pts
I3Wed, Oct 14, 2026 to Wed, Oct 28, 20260 open · 11/11 pts done · 4 must
Calculations
Done2 ptsNeeds
Blocks
Calculations
Done2 ptsNeeds
Blocks
Calculations
Done2 ptsNeeds
Blocks
Calculations
Done2 ptsNeeds
Blocks
Calculations
Done1 ptsNeeds
Blocks
Calculations
Done2 ptsNeeds
Blocks
I4Wed, Oct 28, 2026 to Wed, Nov 11, 20260 open · 19/19 pts done · 2 must
Accounts
Done1 ptsProperty Inputs
Done1 ptsCalculations
Done2 ptsNeeds
Blocks
Calculations
Done3 ptsNeeds
Rates and Rules
Done2 ptsValidation and Hardening
Done2 ptsSubscription and Business Model
Done1 ptsSubscription and Business Model
Done2 ptsCalculations
Done2 ptsRates and Rules
Done1 ptsAccounts
Done2 pts
Roster (5)
- JalenSM
Developer
- Jayden
Developer
- Nikolai
Developer
- Reshmala
Designer
- Sonique
Business Analyst
Sprint goals (why this sprint is valuable for Team 1)
Sign in as this team's Scrum Master or the Product Owner to set the sprint goals.